PM FPX 5334 Assessment 2

Assessment Overview

PM FPX 5334 Assessment 2: focuses on Earned Value Analysis (EVA) for NearlyFree.com’s New Employee Orientation (NEO) design. The design is behind schedule and over budget, so EVA is used to estimate performance, cast completion costs, and recommend a budget reversal strategy. Crucial criteria similar to cost friction (CV), schedule friction (SV), cost performance indicator (CPI), and schedule performance indicator (SPI) companion decision-timber. 

What’s Included:

Sample Assessment Paper

Optimizing Project Management: An In-Depth Analysis of NearlyFree.com’s Budget Challenges

PM FPX 5334 Assessment 2:Introduction

NearlyFree.com is already having issues with a project that has run at a cost of an initial $25,000. The company is at 43% completion and has had major flaws and now needs professional help in managing its project services. An examination of a financial statement shows a primary discrepancy on the earned value, which has been significantly under-budgeted. The main objective of NearlyFree.com‘s project is to design and deploy an automated web-based training system for the new hires. The project focuses on automating the New Employee Orientation (NEO) process, thus lessening the workload and resource demand.

Project Overview

The current project scope defines a 92-day timeline with a budget approved for $22,300. This report provides an in-depth analysis of the earned value method, assesses project success, and makes necessary earned value calculations to facilitate an effective turnaround.

Understanding the Earned Value Technique

The Earned Value (EV) technique is a key project management technique that monitors the project plan, work done, and value of work done. The EV method allows the project manager to determine if the project is on course. By comparing actual and planned spending, the method is useful in informing time management as well as cost management. Action of control is taken against the cost baseline, based on necessary calculations to provide effective reporting of project progress.

Key Inputs in Earned Value Analysis

  • Earned Value (EV): It estimates the value of actual achievement of activities as of the date of analysis.
  • Planned Value (PV): It estimates the budgeted expenditure of funds based on the project schedule as of the date of analysis.
  • Actual Cost (AC): This is the actual cost incurred as of the date of analysis.

Essential Calculations

Cost Variance (CV)

Cost variance represents the budget difference at the analysis moment and is calculated by the following formula:

[\text{Cost Variance (CV)} = \text{Earned Value (EV)} – \text{Actual Cost (AC)}]

Cost Performance Index (CPI)

This index represents the project’s budget difference in relation to its total size:

[\text{Cost Performance Index (CPI)} = \frac{\text{Earned Value (EV)}}{\text{Actual Cost (AC)}}]

Schedule Variance (SV)

Schedule variance is the project schedule variation at the analysis date and is calculated as follows:

\text{Schedule Variance (SV)} = \text{Earned Value (EV)} – \text{Planned Value (PV)}]

Schedule Performance Index (SPI)

This metric provides information regarding the project performance against its planned schedule: [

\text{Schedule Performance Index (SPI)} = \frac{\text{Earned Value (EV)}}{\text{Planned Value (PV)}}] 

Analysis of Schedule Variance (SV)

The schedule variance indicates that the project is behind schedule: [ Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV) ] [ SV = $12,373.95 – $20,453.95 = -$8,080.00 ]

Cost Variance (CV) Insights

The cost variance reflects the monetary variances from the initial budgeting:

Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC)

] [

CV = $12,373.95 – $16,373.95 = -$4,000.00]

Performance Indices Interpretation

  • Schedule Performance Index (SPI): With a reading of 0.60, the SPI reflects that the project is critically behind schedule because an SPI reading below 1 reflects delays.
  • Cost Performance Index (CPI): The value of 0.76 for CPI means that for each dollar spent, less value is being obtained than expected, indicating potential cost overruns.

Budget at Completion (BAC) and Estimate at Completion (EAC)

The Budget at Completion (BAC) for NearlyFree.com is $22,300. However, the Estimate at Completion (EAC), or projected total cost of the project to date based on existing performance, is as given below: [ \\\\text{Estimate at Completion (EAC)} = \\\\text{Actual Cost (AC)} + \\\\frac {(\\\\text{Budget at Completion (BAC)} – \\\\text{Earned Value (EV)})} {\\\\text{Cost Performance Index (CPI)}} ] [ \\\\text{EAC} = \\\\$16,373.95 + \\\\frac{(\\\\$22,300 – \\\\$12,373.95)}{0.76} = \\\\$29,434.54 ]

Strategic Budget Turnaround

Utilizing Earned Value Analysis (EVA) is necessary in order to track progress on the project, estimate completion time, and detect budget and schedule variances. NearlyFree.com‘s first EVA for the NEO project says that it is more than 50% behind schedule and that there is a total budget overrun. A more accurate EVA would have given a more definite timeline and budget.

Conclusion

In order to guarantee project success, NearlyFree.com will have to lengthen the time horizon and revisit the budget, raising the Estimate at Completion to $29,434.54 from $22,300. Such revisions are unavoidable since going beyond the initial budget or timeline may compromise stakeholder confidence, negatively impact stock market performance, and hurt the firm’s financial standing. An accurate project schedule would avoid the threat of additional cost overruns and guarantee successful project completion.

References

Cullen, S. (2nd August 2016). Earned value analysis. WBDG. https://www.ncbi.nlm.nih.gov/pmc/articles/PMC7732517/

Haughey, D. (26th July 2020). What is earned value? ProjectSmart.  https://www.ahrq.gov

Peng, B. (10th April 2018). The earned value method. Project Engineer. Project Engineer.

Usmani, F. (18th August 2020). Planned value (PV), earned value (EV), & actual cost (AC) in project cost management. PM Study Circle. PM Study Circle https://www.nursingtimes.net/leadership/

Step-by-Step Guide

  1. Define Project Scope & Budget – 92-day design with an original budget of $22,300. 
  2. Collect crucial inputs—determine earned value (EV), planned value (PV), and actual cost (AC). 
  3. Calculate Cost and Schedule Variances—CV = EV – AC; SV = EV – PV. 
  4. cipher Performance Indices – CPI = EV/AC; SPI = EV/PV. 
  5. Assess Budget at Completion (BAC)—Original budget planned for design completion. 
  6. Estimate at Completion (EAC)—Projected total cost grounded on current performance 
  7. EAC = AC(BAC – EV) CPIEAC = AC frac{( BAC – EV)} { CPI} EAC = AC CPI (BAC – EV) 
  8. Interpret Results – Identify schedule detainments (SPI < 1) and cost overruns (CPI < 1). 
  9. Recommend Turnaround Strategy – Acclimate schedule, increase budget to $29,434.54, and cover progress using EVA. 

Frequently Asked Questions (FAQs)

Integrity Note

Use this example for learning and structure only. Do not submit as your own work.
We are an independent resource and are not affiliated with any university.

Essay-Writing-Service-For-Students-Best-Essay-Writer-Online.png

“I paid the service to write my research paper.” They wrote an excellent paper with a lot of research and correct citations. “Great excellent work!”

Order ID # 00889

BSN - Capella University

Jonathan Nicole

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : BSN, MSN

Jessica Walker

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : MSN, DNP

Denis Peterson

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : DNP, PSY

How it Works

We provide services to registered nurses who are taking classes toward their BSN or MSN degrees.

You cannot copy content of this page

Nursing Papers Help even with a 3-hour deadline!

Get Any Assessment For Free

Verification is required to avoid bots.