PM FPX 5333 Assessment 2

Assessment Overview

PM FPX 5333 Assessment 2 uses Earned Value Analysis (EVA) to estimate the NearlyFree.com design’s progress, schedule, and budget. The design is behind schedule and over budget, with crucial performance pointers (CPI and SPI) pressing inefficiencies. EVA helps read total costs, identify detainments, and recommend strategies to realign the design for successful completion. 

What’s Included:

Sample Assessment Paper

Optimizing Project Management with Earned Value Analysis: A Case Study of NearlyFree.com

Introduction

NearlyFree.com is presently working on a project whose original budget was $25,000. With the project standing at 43% completion level, the company has learned from its errors and has asked for our project management services. A rigorous examination of the project’s annual accounts reveals that the earned price is within budget. The project is trying to create and share an automated web-based training system for new employees, thus reducing the fee and reducing the staff resources required for new employee orientation (NEO) training.

The scope of the project defines the 92-day program with an approved budget of $22,300. The report will investigate the earned price technology (if applicable), evaluate the current status of the project, and conduct the earned price calculation required to enable an effective turnaround strategy.

Understanding the Earned Value Technique

Acquired price (EV) technology is an essential method of tracking the relationship between a project plan in project management and the actual value and progress of the work. The technology can be used to determine whether the project should have utilized how much time should have been utilized depending on the work done by evaluating the project. Control on the project is carried out against the cost basis by utilizing earned value, which is in the form of calculating and reporting a collection of key performance indicators of the actual progress.

PM FPX 5333 Assessment 2:Key Inputs in Earned Value Analysis

  • Earned Value (EV): The actual current progress of the task as of the date of analysis of the task.
  • Planned Value (PV): Estimated cost of money spent up to the analysis date according to the calculation from the project schedule.
  • Actual Cost (AC): Actual cost of money actually spent over the period under analysis.

Essential Calculations in Earned Value Management

In determining how well or poorly the project is performing, certain very useful calculations can be done:

Cost Variance (CV)

Cost Variance (CV) specifies by how much the project is ahead or behind schedule at any point in time. It can be calculated as

[ Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC) ]

For the project:

[ CV = $12,373.95 – $16,373.95 = -$4,000.00 ]

A cost variance of -$4,000 indicates that the project is running behind budget, while the optimum variance will be higher or zero.

Schedule Variance (SV)

Schedule Variance (SV) checks whether a project is ahead or behind time. The formula is

[ Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV) ]

For this project:

[ SV = $12,373.95 – $20,453.95 = -$8,080.00 ]

This negative schedule variance indicates that the project is way behind schedule.

Performance Indices

  • Schedule Performance Index (SPI) measures the effectiveness of the project in relation to its planned completion:

[ SPI = Earned Value (EV) / Planned Value (PV) ]

For this project:

[ SPI = $12,373.95 / $20,453.95 = 0.60 ]

An SPI of 0.60 indicates that there is a lag in the progress of the project, as any value below 1 indicates the project is behind.

  • Cost Performance Index (CPI) gauges the financial performance of the project:

[ CPI = EV / AC ]

For this project:

[ CPI = $12,373.95 / $16,373.95 = 0.76 ]

A CPI of 0.76 suggests that the project is facing financial issues, since a CPI of less than 1 indicates inefficiency in cost control.

Project Budget and Future Projections

Budget at Completion (BAC)

Budget at Completion (BAC) refers to the total budget spent on the project. For NearlyFree.com, BAC is $22,300 initially.

Estimate at Completion (EAC)

Estimate at Completion (EAC) predicts the total cost of the project using its history. The EAC formula is as follows:

[ EAC = Actual Cost (AC) + (Budget at Completion (BAC) – Earned Value (EV)) / Cost Performance Index (CPI) ]

For this project:

[EAC = $16,373.95 + ($22,300 – $12,373.95) / 0.76]

[EAC = $16,373.95 + $13,060.59]

[ EAC = $29,434.54 ]

Recommended Budget Turnaround Strategy

Earned Value Analysis (EVA) is a common method of assessing project progress, forecasting completion time and final cost, and measuring schedule and budget variances in terms of amounts. EVA calculates whether cost, schedule, and work accomplished are according to project expectations based on the quantification of planned work and actual performance.

The latest EVA shows that NearlyFree.com‘s NEO initiative is more than 50% behind schedule, and there are gigantic overruns in the budget. A better-planned EVA would have anticipated improved budget requirements and completion times. The updated EAC shows that the project will cost more, from the original $22,300 to a new estimate of $29,434.54, which is a massive increase of over $7,000.

To mitigate these issues, it is advised that NearlyFree.com delay the project timeline. This would ensure sufficient time to finish the project, potentially enhancing earned value and reducing the incomplete work percentage.

Conclusion

Scheduling and budget changes are essential in guaranteeing a successful project. Cost overruns can potentially ruin stakeholder confidence, which could affect the performance of the company in the marketplace and funding for future projects. Through the assistance of a more precise project schedule and by executing the Earned Value Technique properly, NearlyFree.com can manage its present challenges and enhance overall project management practices.

References

Step-by-Step Guide

  1. Define Key Metrics – Identify Earned Value (EV), Planned Value (PV), and Actual Cost (AC). 
  2. Calculate Cost Friction (CV)—Determine budget performance CV = EV – AC. 
  3. Calculate Schedule Friction (SV)—Determine schedule performance SV = EV – PV. 
  4. cipher Performance Indices – SPI = EV/PV (schedule effectiveness), CPI = EV/AC (cost effectiveness). 
  5. Assess Budget at Completion (BAC)—Original design budget. 
  6. Estimate at Completion (EAC)—Forecast total design cost using EAC = AC (BAC – EV) CPI. 
  7. Develop Turnaround Strategy – Acclimate design timeline and examiner EVA to ameliorate cost and schedule performance. 

Frequently Asked Questions (FAQs)

Integrity Note

Use this example for learning and structure only. Do not submit as your own work.
We are an independent resource and are not affiliated with any university.

Essay-Writing-Service-For-Students-Best-Essay-Writer-Online.png

“I paid the service to write my research paper.” They wrote an excellent paper with a lot of research and correct citations. “Great excellent work!”

Order ID # 00889

BSN - Capella University

Jonathan Nicole

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : BSN, MSN

Jessica Walker

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : MSN, DNP

Denis Peterson

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : DNP, PSY

How it Works

We provide services to registered nurses who are taking classes toward their BSN or MSN degrees.

You cannot copy content of this page

Nursing Papers Help even with a 3-hour deadline!

Get Any Assessment For Free

Verification is required to avoid bots.